The state of the purepath is grayed

Hi Team,


The state of the purepath is grayed : Unable to determine PurePath success because of the following reasons:


Path Corrupted:

Events of this PurePath have been skipped by one of the involved agents. Maybe there was a network or load problem


Path Corrupted:

Not the whole PurePath has been captured as the node limit is exceeded or due to a too high subpath nesting depth


Please advise


Thank you



3 REPLIES 3

sebastian_kryst
DynaMight Leader
DynaMight Leader

It sometimes happened. Check place on the purepath where corruption is marked. Most of the time this is because of complexity of purepaths, where one of async threads doesn't come back in time, agent is waiting for response. If yes, it is option to extend time, where Dynatrace is waiting for responses but this has extra cost for appmon server performance.

Sebastian


Hello sebastian k. ,


Thank you for your comment, so I'm not sure what you mean "Check place on the purepath where corruption is marked. " and could you please advise to extend time.


Thank you,


When you go down along purepath, on some place you will see node "Purepath corrupted"