custom baselines in dcrum

erenedo
Organizer

Hi,

Our custom wants to create a baseline for which we indicate some values and DCRUM gets that information to calculate a baseline. I guess I can do that selecting the option "Override computed baselines with manual data", right?

And I guess I can combine this way to calculate the baseline with "Average baseline" mode, right?

If anything is not clear don't hesitate asking me.

Thanks in advance.

Elena.

1 REPLY 1

david_n
Inactive

Hello Elena,

Yes, the override computed baselines option is meant for this scenario. To use the manual baselines it requires at least Pinned or Average mode to be selected.

For more information, here is a helpful link:

https://community.dynatrace.com/community/display/DCRUMDOC/Overriding+calculated+baselines+with+manually+imported+values

Thanks,

David Nicholls