Hi All,
Kindly help in below scenario.
We have one agent managed (on prem) setup of one agent
monitoring multiple applications.
Out of all servers on which one agent is installed , 35% of
application servers’ migrating to new data center as part of DC migration
process, in the process deployment will happen on new physical hosts.
- All app servers will
undergo IP change - Back-up taken of old app
servers will be installed on new physical app servers to make it active. - Active gate &
Managed server to have same IP & host name as they NOT getting
migrated.
My query is :
-
Since one agent already
installed on all app servers, how the migrated app servers will be
affected if -
If app servers IP is
changed & host name remains same -
If app servers IP is
changed & host name is changed too
What approach to be taken in the above case to minimize
reconfiguration ? or it will require fresh agent installation & complete
reconfiguration of dashboards & alerts threshold?
Pls suggest.
2nd scenario is
If my active gateway & managed server will undergo
migration
- Will licenses still be
valid even after IP is changed & hostname is changed too - Will my licenses still
be valid even after IP is changed & hostname remains same.