We’re planning to move our existing Production cluster node from virtualized environment to a new On - premise environment.
3 nodes are installed on a virtualized environment(AWS) and the new production nodes will be 5 physical machines with better CPU/RAM/Storage configuration.
According to the Dynatrace documentation (1, 2, 3) new nodes “must” be in identical configuration as the old ones, so if we go with the data replication method by adding new cluster nodes, we will have incompatibilities.
How do you think we should proceed? What are the pre-requisites we should be taking care of?
Hi, since we are migrating from cloud to on-prem, can you please guide me with command to check which agents are connected on managed cluster node, as we had raised the port opening directly from application farm to Managed cluster node.