03 May 2019 02:18 PM
Hi All,
Kindly help in below scenario.
We have one agent managed (on prem) setup of one agent
monitoring multiple applications.
Out of all servers on which one agent is installed , 35% of
application servers’ migrating to new data center as part of DC migration
process, in the process deployment will happen on new physical hosts.
My query is :
What approach to be taken in the above case to minimize
reconfiguration ? or it will require fresh agent installation & complete
reconfiguration of dashboards & alerts threshold?
Pls suggest.
2nd scenario is
If my active gateway & managed server will undergo
migration
Solved! Go to Solution.
16 Apr 2020 03:21 PM
If the IP's change and the host remains, you will not see any adverse affects. The issue is when a host looses the GUID for the oneagent, then the system will give it a new GUID and be a new instance within the UI. But simply updating IP's will not have any issues as the change will be reflected under the properties of the host(s) in question. Just make sure if you need any firewall rules in place to have them applied when the IP's change otherwise it wont be able to communicate.
Activegate and clusters, now that might be an issue, I'd recommend reaching out to support first for those